Kentucky • Mechanics Lien Deadlines

Kentucky Mechanics Lien Deadline Calculator

Learn the exact preliminary notice and lien filing deadlines in Kentucky. Then jump into the LienDeadline calculator to see your real project dates in 0.3 seconds.

Calculate my Kentucky deadline →

Free for the first 3 calculations. No credit card required.

Kentucky Lien Deadline Overview

Preliminary Notice Deadline

Notice must be filed within 120 days after last furnishing for claims over $1000; 75 days for claims $1000 or less

Mechanics Lien Filing Deadline

Lien filing deadline is 6 months (180 days) after last furnishing

Typical Projects

Building material suppliers, lumber yards, concrete and rebar suppliers working on private construction projects in Kentucky.

This page is a simplified summary for material suppliers and does not replace advice from a construction attorney.

How lien deadlines work in Kentucky

In Kentucky, material suppliers must follow specific deadlines to protect their lien rights. The preliminary notice deadline is notice must be filed within 120 days after last furnishing for claims over $1000; 75 days for claims $1000 or less. The mechanics lien filing deadline is lien filing deadline is 6 months (180 days) after last furnishing. Missing either deadline results in complete loss of lien rights for that project.

Preliminary notice rules

  • Notice must be filed within 120 days after last furnishing for claims over $1000; 75 days for claims $1000 or less
  • Notice of Intention required for material suppliers
  • Notice of Intention required for material suppliers

Mechanics lien filing rules

  • Suit to enforce must be filed within 1 year of lien recording
  • Lien filing deadline is 6 months (180 days) after last furnishing
  • Mechanic's Lien must be filed within deadline

Ready to see your real project dates?

Enter your Kentucky project dates once. LienDeadline shows you preliminary notice and lien filing deadlines in 0.3 seconds across all supported states.

Open the calculator →

Frequently asked questions

What is the mechanics lien deadline in Kentucky?

Lien filing deadline is 6 months (180 days) after last furnishing

Does Kentucky require a preliminary notice?

Notice must be filed within 120 days after last furnishing for claims over $1000; 75 days for claims $1000 or less

What happens if I miss the deadline?

You lose your legal right to file a lien for that project, even if you're still owed money. That's why many suppliers use automated deadline tools instead of spreadsheets.