Virginia • Mechanics Lien Deadlines

Virginia Mechanics Lien Deadline Calculator

Learn the exact preliminary notice and lien filing deadlines in Virginia. Then jump into the LienDeadline calculator to see your real project dates in 0.3 seconds.

Calculate my Virginia deadline →

Free for the first 3 calculations. No credit card required.

Virginia Lien Deadline Overview

Preliminary Notice Deadline

Must serve notice within 90 days of last furnishing

Mechanics Lien Filing Deadline

150 days after last furnishing labor or materials

Typical Projects

Building material suppliers, lumber yards, concrete and rebar suppliers working on private construction projects in Virginia.

This page is a simplified summary for material suppliers and does not replace advice from a construction attorney.

How lien deadlines work in Virginia

In Virginia, material suppliers must follow specific deadlines to protect their lien rights. The preliminary notice deadline is must serve notice within 90 days of last furnishing. The mechanics lien filing deadline is 150 days after last furnishing labor or materials. Missing either deadline results in complete loss of lien rights for that project.

Preliminary notice rules

  • Must serve Notice within 90 days of last furnishing
  • Notice must be served before lien filing
  • Must serve notice within 90 days of last furnishing

Mechanics lien filing rules

  • Lien must be filed within 150 days of last furnishing
  • Notice must be served before lien filing
  • 150 days after last furnishing labor or materials

Ready to see your real project dates?

Enter your Virginia project dates once. LienDeadline shows you preliminary notice and lien filing deadlines in 0.3 seconds across all supported states.

Open the calculator →

Frequently asked questions

What is the mechanics lien deadline in Virginia?

150 days after last furnishing labor or materials

Does Virginia require a preliminary notice?

Must serve notice within 90 days of last furnishing

What happens if I miss the deadline?

You lose your legal right to file a lien for that project, even if you're still owed money. That's why many suppliers use automated deadline tools instead of spreadsheets.