Skip to content

Avoid a $75,000+ loss from a missed deadline

Idaho Lien Deadlines for Material Suppliers

Idaho requires lien filing within 90 days from last furnishing.

Calculate Your Idaho Deadline

Try 3 free (no email) + 7 more after emailUp to 10 total • no credit card

Idaho is High Risk for Suppliers

Notice must be served on the owner by personal delivery or certified mail within 5 days of filing the lien.

Idaho Mechanics Lien Deadlines (Updated 2026)

Deadline TypeTimingDetails
Preliminary/NoticeNot specified(Do not invent)
Lien Filing90 days from last furnishingMust file lien by 90 days from last furnishing.
Notice MethodPersonal delivery or certified mailServed on owner within 5 days of filing.
Enforcement6 months from date lien filedSuit to enforce must be filed within 6 months.
StatutesIdaho Code §45-501; §45-507; §45-510

Common Supplier Mistakes in Idaho

Missing Preliminary Notice

Failing to send the required preliminary notice is the most common reason suppliers lose their lien rights in Idaho.

Late Lien Filing

The lien must be filed by the specific deadline. Even one day late invalidates the lien.

Missing Enforcement Deadline

Enforcement must occur within the statutory period after filing.

Not Sure Which Deadline Applies?

Calculate your Idaho lien deadline in seconds.

Calculate Your Idaho Deadline

Select Idaho in the calculator to get your specific deadline.

Frequently Asked Questions

What notices are required?

Not specified in the provided text.

When must the lien be filed?

90 days from last furnishing.

What is the enforcement period?

6 months from date lien filed.

What statutes apply?

Idaho Code §45-501; §45-507; §45-510

Disclaimer: This content is for informational purposes only and does not constitute legal advice.