Nebraska Lien Law Deadlines for Suppliers and Subcontractors
Nebraska gives suppliers and subcontractors 120 days after their final furnishing to record a lien with the county register of deeds, and 2 years after recording to enforce it. There is no mandatory preliminary notice, but owner-occupied homes have extra notice rules.
Try 3 free calculations, then create a free account No credit card required
Risk context
Nebraska is High Risk for Suppliers
A protected party under §52-129 can include an owner who occupies or intends to occupy a residence and specified related obligors, subject to the four-unit and nonresidential-use qualifications. For non-prime claimants, §52-136 limits the lien by the qualifying unpaid balance when notice is received. A supplier contracting directly with the owner may be a prime contractor; do not automatically apply the downstream cap. Under §52-140, a demand by an eligible party can shorten the period to thirty days from receipt. The statute permits the alternative recorded affidavit when total contract payment is not yet due. Preserve the demand, receipt date and payment terms for review.
Deadline schedule
Nebraska Mechanics Lien Deadlines (Updated 2026)
Scroll sideways to see all deadline details.
| Deadline Type | Timing | Details |
|---|---|---|
| Lien Filing Deadline | 120 days after last furnishing | Must be filed with the county recorder/clerk. In Nebraska, record it with the register of deeds for the county within 120 days after your final furnishing (Neb. Rev. Stat. § 52-137). |
| Preliminary Notice | None required | A protected party under §52-129 can include an owner who occupies or intends to occupy a residence and specified related obligors, subject to the four-unit and nonresidential-use qualifications. For non-prime claimants, §52-136 limits the lien by the qualifying unpaid balance when notice is received. A supplier contracting directly with the owner may be a prime contractor; do not automatically apply the downstream cap. |
| Copy to Owner | Within 10 days after recording | Where the protected-party rule applies, send the contracting owner a copy within ten days after recording under §52-135(3). This is not a universal copy deadline for every owner. |
| Enforcement Deadline | 2 years after filing | Lawsuit to foreclose on the lien must be filed by this date. Under §52-140, a demand by an eligible party can shorten the period to thirty days from receipt. The statute permits the alternative recorded affidavit when total contract payment is not yet due. Preserve the demand, receipt date and payment terms for review. |
| Statutes | Governing statutes | Neb. Rev. Stat. §52-125; §52-134; §52-137; §52-140; also §§ 52-135 and 52-136. |
Supplier pitfalls
Common Supplier Mistakes in Nebraska
Failing to track the 120-day filing window
Nebraska's 120 days run from your final furnishing. With no preliminary notice to prompt you, the recording deadline is the first hard date on most jobs, so track the last delivery date on every account.
Sending the owner notice late on a home
A protected party under §52-129 can include an owner who occupies or intends to occupy a residence and specified related obligors, subject to the four-unit and nonresidential-use qualifications. For non-prime claimants, §52-136 limits the lien by the qualifying unpaid balance when notice is received. A supplier contracting directly with the owner may be a prime contractor; do not automatically apply the downstream cap.
Missing the 2-year enforcement deadline
Ordinarily enforce within two years after recording. Under §52-140, a demand by an eligible party can shorten the period to thirty days from receipt. The statute permits the alternative recorded affidavit when total contract payment is not yet due. Preserve the demand, receipt date and payment terms for review.
Deadline calculator
Not Sure Which Nebraska Deadline Applies?
Check which supplier deadlines the calculator can evaluate for your Nebraska project.
Check Nebraska project coverageCoverage depends on the project type, who hired you, and the facts you can confirm.
Common questions
Frequently Asked Questions
What are the Nebraska lien law deadlines?
Record the lien with the county register of deeds within 120 days after your final furnishing and enforce it within 2 years after recording. Where §52-135’s protected-party rule applies, send the contracting owner the recorded copy within ten days. Review the statutory category, including qualifying intended occupancy, rather than assuming every residential owner has the same status.
Does Nebraska require a preliminary notice?
There is no universal preliminary-notice duty. A protected party under §52-129 can include an owner who occupies or intends to occupy a residence and specified related obligors, subject to the four-unit and nonresidential-use qualifications. For non-prime claimants, §52-136 limits the lien by the qualifying unpaid balance when notice is received. A supplier contracting directly with the owner may be a prime contractor; do not automatically apply the downstream cap.
How long do I have to enforce a Nebraska lien?
2 years after recording (Neb. Rev. Stat. § 52-140(1)). Under §52-140, a demand by an eligible party can shorten the period to thirty days from receipt. The statute permits the alternative recorded affidavit when total contract payment is not yet due. Preserve the demand, receipt date and payment terms for review. See how long a mechanics lien lasts for how expiration works.
Are these the 2024 Nebraska lien law deadlines?
Yes. Neb. Rev. Stat. §§ 52-137 and 52-140 have not been amended since 1981, and §§ 52-135 and 52-136 were last amended in 2003, so these deadlines applied in 2024 and remain current as of our September 2026 review.