West Virginia Lien Law Deadlines for Suppliers and Subcontractors

In West Virginia, a supplier hired by a contractor or subcontractor must give the owner the statutory sworn notice and record within one hundred days after last furnishing under §38-2-11. A direct-owner supplier follows §38-2-10’s recording route. Section 38-2-34(a) requires commencement of enforcement within six months after filing the lien notice. Subcontractors count their 100 days from completing the subcontract. An early owner warning does not resolve the later perfection and enforcement requirements.

Try 3 free calculations, then create a free account No credit card required

West Virginia is High Risk for Suppliers

For an indirect supplier covered by §38-2-11, the one-hundred-day step includes both the statutory owner notice and county recording. Do not impose that section's owner-notice route on a direct-owner supplier governed by §38-2-10. The owner can also demand an itemized account at any time, and you have only 10 days to answer. Payments the owner makes to the contractor generally do not reduce your lien, but since July 1, 2015 owners of single-family and owner-occupied homes can defend on that ground.

West Virginia Mechanics Lien Deadlines (Updated 2026)

Scroll sideways to see all deadline details.

Deadline TypeTimingDetails
Lien Filing Deadline100 days from last furnishingMust be filed with the county recorder/clerk. In West Virginia, record the notice of lien with the clerk of the county commission for the county where the property is located (W. Va. Code §§ 38-2-7, 38-2-11).
Notice to Owner (Indirect Supplier)Within the same 100 daysUnder §38-2-11, serve the owner or the owner's authorized agent with a sworn notice of mechanic's lien, including an itemized account, by a method allowed for serving a legal notice or summons. If ordinary service cannot be completed, preserve the address search and any officer return and obtain qualified review of the applicable substituted-service procedure. Do not assume posting or publication is an interchangeable substitute for ordinary service.
Subcontractors100 days after completing the subcontractA subcontractor's 100 days run from completion of its subcontract rather than its last delivery, with the same service and recording steps (W. Va. Code § 38-2-9).
Preliminary NoticeNone requiredAn early owner warning under §38-2-20 does not establish completion of the later perfection steps. For an indirect supplier, §38-2-11 separately requires owner notice and recording within one hundred days; direct-owner suppliers must review §38-2-10 instead.
Itemized Account on DemandWithin 10 days of the owner's written demandIf the owner demands an itemized account in writing, deliver it within 10 days of receiving the demand. Otherwise the owner and property are released from your lien for everything furnished before the demand (W. Va. Code § 38-2-19).
Enforcement DeadlineWithin six months after filing the lien notice§38-2-34(a) requires commencement of an action in circuit court within six months after filing the notice in the clerk’s office, or the lien is discharged. Obtain qualified review of parties, service and any reliance on another lienholder’s action; recording alone does not commence enforcement.
Homeowner DefenseSince July 1, 2015On an existing single-family home, a residence built for the owner to occupy as a primary residence, or an owner-occupied single-family home, the owner can defend by showing it owes the contractor less than your lien, or nothing. The owner-occupied category does not cover a developer or builder of multiple homes, except the home it lives in (W. Va. Code §§ 38-2-21(b), 38-2-34(b)).
Public Project IntakeIdentify the public owner, contract and bondObtain the contract and payment-bond record and qualified public-work review. Do not assume the private-property lien procedure applies to a public project.
StatutesGoverning statutesWV Code §38-2-1 et seq.; §§8-13 (that is, §§ 38-2-8 to 38-2-13). Key sections: §§ 38-2-4, 38-2-7, 38-2-11, 38-2-19, 38-2-21, and 38-2-34.

Common Supplier Mistakes in West Virginia

Recording without serving the owner

For an indirect supplier under §38-2-11, both steps must happen within one hundred days after last furnishing: serve the owner with the sworn notice of lien by a method allowed for serving a summons, and record the notice with the clerk of the county commission. If the lien is not perfected within those 100 days, it is discharged.

Ignoring the owner's demand for an itemized account

If the owner asks in writing for an itemized account of what you furnished, you have 10 days from receiving the demand. Miss it and the owner and property are released from your lien for everything furnished before the demand.

Assuming the owner's payments cannot reduce your lien on a home

West Virginia generally protects your lien even after the owner has paid the contractor. Since July 1, 2015, that protection does not hold on single-family and owner-occupied homes: the owner can defend by showing it owes the contractor less than your lien.

Treating recording as the end of the process

Give counsel the recorded claim, contract chain, service evidence and any other lien proceedings promptly. Commence the circuit-court action within six months after filing the lien notice under §38-2-34(a). Confirm proper parties and procedure before relying on enforcement or intervention.

Not Sure Which West Virginia Deadline Applies?

Check which supplier deadlines the calculator can evaluate for your West Virginia project.

Check West Virginia project coverage

Coverage depends on the project type, who hired you, and the facts you can confirm.

Frequently Asked Questions

What are the West Virginia lien law deadlines?

For indirect material suppliers under §38-2-11, give the statutory owner notice and record within one hundred days after last furnishing; subcontractors have their own completion trigger. A direct-owner supplier follows §38-2-10, so establish the buyer relationship before assuming the same service duty. Commence the separate enforcement action within six months after filing the lien notice under §38-2-34(a), with qualified review of the procedure.

Does an early warning letter finish the lien process?

No. Preserve the letter and establish the buyer relationship. An indirect material supplier must separately follow §38-2-11’s owner-notice and recording requirements; a direct-owner supplier follows §38-2-10. Obtain review of any additional effect under §38-2-20 rather than treating the early letter as a substitute.

How long do I have to enforce a West Virginia lien?

Under §38-2-34(a), commence an action in circuit court within six months after filing the lien notice in the clerk’s office, or the lien is discharged. Obtain qualified review of any reliance on another lienholder’s action and the parties and procedure needed to enforce your claim. Keep the filing date and all court papers together.

Why does the supplier’s buyer matter?

A supplier contracting directly with the owner and one supplying a contractor or subcontractor follow different statutory perfection provisions (§§38-2-10 and -11). Keep the actual purchase order, contract chain and delivery records, and obtain qualified review of the applicable notice, recording and enforcement procedure.